Normandale Park D Neighborhood Reconstruction

Construction is scheduled to begin Spring 2018 and the project has a substantial completion date of August 31. View the project area map (PDF) to see all the streets within this project.

Project Updates

Sign up for City Extra emails to receive weekly project updates.

Project Scope

This project will include complete reconstruction of the pavement, new concrete curb and gutter, replacement of watermain and water services, repairs to portions of the sanitary sewer and improvements to the storm sewer system. 

Special Assessments

The full costs of the roadway improvements are assessed to the property owners within the project area. The pending special assessment is $14,920 per property. The final bill for the special assessment will be mailed to property owners in September 2019 and can be paid off over 15 years with interest. Additional payment options and more information can be found here.  

Resident Correspondence and Planning Documents

View our correspondence with residents, meeting presentations and other relevant documents.
(Select **Browse all Folders** - Engineering - Projects - 2018 - Normandale Park D)

  1. Torgerson1

    Drew Torgerson

    Engineering Technician
    Phone: 952-826-0444

Have special events or home improvement projects planned during construction? Contact Drew to coordinate schedules.

Emergencies: 911
Non-emergencies after hours: 952-826-1600

Site Safety
Safety is our #1 priority. Exercise caution when driving in areas where crews are working and keep children away from construction sites.