Ongoing Construction Update

The expansion of the North Parking Ramp is now complete! This ramp provides nearly 550 public parking stalls - free of charge - for customers and clients. 

The construction of the Nolan Mains apartments and new Center Parking Ramp continues to be on schedule for completion in Fall 2019. When complete, this project will feature 100 new apartment homes, new retail shops, and more than 120 stalls of indoor customer parking all centered around a series of pedestrian walkways and outdoor public plazas. 

Regular construction updates will be posted on this page.

Market Street Construction Update

Now that the 50th & France North Ramp Expansion is complete we are thrilled to deliver additional free parking. Thank you to all of the customers and businesses that were patient while we worked to construct the additional public parking to serve Edina's downtown at 50th & France.

Comcast Work Throughout Edina

The work you see taking place in the 50th & France District and adjoining neighborhoods is a Comcast city-wide project. The work will include replacing overhead coax and drilling below ground for fiber and above ground devices. The equipment you see on the corner of France Avenue and Market Street are heaters that are thawing the ground for future cable installation. The work schedule for this upcoming week is not available at this time, as permits are pending approval.

Construction Coffee Break

Join City of Edina, Nolan Mains and 50th & France Association representatives from 8 to 9 a.m. Wednesday, March 27, for an update on the Market Street Project. Bring your questions and meet with your business colleagues. The coffee break will be at D'Amico & Sons at 50th & France.

Construction Activities Week of March 18-22, 2019

Nolan Mains Construction

The building structure continues to take shape:

  • Major concrete deck pour will occur Monday, March 18, for the third floor of the east building (rescheduled due to rain)
  • Exit from the North Ramp will remain open during this pour
  • Total deck pours: 24 completed of 28
  • Exterior wall and window installation, west building: 55 percent complete
  • Steel stud and exterior wall framing, first floor retail area, west building: 70 percent complete
  • Beginning window installation first floor retail area, west building
  • Interior wall framing fourth floor, west building: 90 percent complete
  • Despite many days of rain, the completion dates are on schedule, Nov. 1, west building and Dec. 20, east building
All work is subject to change due to weather.

Parking Update

  • Exit from the North Ramp remains open in both directions
  • Market Street continues to be one way going east - east of the North Ramp exit

      Parking Map

      50th & France Parking Map

      Additional Information

      Stay informed! Sign up for City Extra emails for major updates.

      Don't know much about the project? Watch this kickoff video from 2017: