Countryside G Neighborhood Roadway Reconstruction

Construction began April 10 and will be substantially completed by September 29.

Project Updates

Sign up for City Extra emails to receive weekly project updates. Click on the project area map to see all the streets in the project area.

The Project

Construction will include new roadways, repairs to portions of the sanitary sewer main pipe, replacement of portions of the water main pipe, new curb and gutter on Berne Circle, Grove Circle, and Olinger Road, and spot repair on Sherman Circle, sump drains in some areas for residents to connect their sump pump discharge, and a sidewalk on the west side of Olinger Road.

The project area is divided into two stages:

  • Stage 1: Olinger Road, Berne Circle, and Grove Circle. Construction in this stage began April 10.
  • Stage 2: Sherman Circle. Construction in this stage is tentatively scheduled for mid-July.

Special Assessment

The full cost of the roadway portion of the project is assessed to residents in the project area. The pending special assessment is $14,766 per property. The final bill for the special assessment will be mailed to you in September 2018, and can be paid off over 15 years with interest. Click here to read the payoff options.

Residents’ Correspondences and Planning Documents

Click here to read our correspondences with residents, meeting presentations, etc. Select Browse all Folders, Engineering, Projects.
 

Derek Northenscold, Engineering Technician

Questions/concerns:
952-826-0448
dnorthenscold@EdinaMN.gov

Emergencies:
Call 911
 
Non-emergencies on the weekends:
Call 952-826-1600
 
Site safety:
Safety is our No. 1 priority. Keep children away from construction sites.
Have special events or home projects planned during construction? Coordinate with Derek.